Child NutritionTDA Timeline
Child Nutrition - Sub Heading
Texas Department of Agriculture
Food and Nutrition Division Annual Timeline
July
Agreement/Application/Renewal
Schedule A
Severe Need Breakfast Application (if applicable).
August through Early September
August 1 - All Provision 2 SFAs that add new campuses or re-structure grades must notify TDA in writing.
Prior to or during the first week of school, the Attachment C: Media release, must be made available to the local news media, the unemployment office and any major employers who are contemplating layoffs in the attendance area of the school.
The Notice/Letter of Predetermined Eligibility should be sent to households of directly certified students as early as possible and preferably before the distribution of application for free and reduced-price meals. TDA FND provides information on directly certified students via CNPIMS (public and charter schools only) by July 1, with quarterly updates provided in October, January, and April.
During the first week of school, applications for free and reduced-price meal benefits and the letter to households must be provided to the parents and/or guardians of all children in attendance at the school.
Certificate of Authority must be completed if authorized representative for the SFA has changed.
Collection Procedures and the selection of the SFA's menu planning system should be submitted to TDA when there is a change.
Start of School + 30 Days
Free and reduced-price meals may be claimed for students based on the prior year's approved applications for a period of no longer then 30 operating days from the first day of school
On-site monitoring of Afterschool Care Program (ASCP) should occur during the first (4) weeks of program operation.
October
A count of the number of applications for free and reduced-price meals should be taken on October 1 of each school year. This is the count used to determine the number of applications to be verified.
November
Verification of applications must be compled by November 15 of each school year. A summary of the SFA's verification effort must be completed and maintained on file.
January
Accuclaim on-site school reviews must be completed and on file in the SFA by February 1 of each school year.
A second on-site monitoring review should be scheduled and conducted for all sites operating a ASCP.
March 1
Verification Summary Report sent to TDA
May 1
Application for SSO completed
May 15
Provision 2 Applications must be postmarked to TDA
May 31
FSMC contracts due to TDA.
June 30
Provision 2 (Base Year) % Calculation Form due to TDA
On-Site monitoring of the SSO should occur during the first three weeks of program operation.